We are delighted to be able to provide an update on the exciting progress of our new school build. The external brickwork and cladding are now complete and the solid fencing around the base of the building has been removed to allow the first stage of the external groundworks to begin. Work is also well underway inside the building with the majority of the internal structure now in place. Power and water have now been connected and the tiling of the new swimming pool is complete. 

At present we are expecting to take ownership of our new school on Monday 17th April 2023.